I am making a z report in which i have to show the actual and commitment values of CJI3 and CJI5.
which table to use ?
I Tried the below steps but did not get the correct values displayed in CJI3 and CJI5.
Actual : Pass project number to prps fetch all the wbs/Object
Pass object to rpsco with wrttp=4 fetch wlp00 to wlp16. Sum wlp00 to wlp16
Commitment : Pass project number to prps fetch all the wbs/Object
Pass object to rpsco with wrttp (21,22) fetch wlp00 to wlp16. Sum wlp00 to wlp16.
Please tell me correct logic .
Second Concern.
2- After Goods Receipt , the value is added in actuals .
Concern: Can we get the value of actual payment against project/wbs only not including GR value.
Please tell